Skip to content

Piping and Instrumentation Diagram (P&ID) Designer Checklist

2009 September 2

Checklists are a good way to avoid making mistakes in any activity. Lets apply them to Piping and Instrumentation Diagrams (P&IDs) in today’s post. This checklist will help a chemical engineer that has to develop brand new P&IDs, or check other’s work.

P&IDs incorporate a lot of the knowledge in any design. They require a lot of data from many different sources and disciplines. And let’s face it, they are one of the few key documents that designers AND business people AND operators will refer to time and time again. You need them as accurate and well thought-out as possible.

Every person will have a different way of thinking, and different responsibilities, and different company practices when they approach a P&ID. As I have worked with them over the years, I built a checklist. Each time myself or a team mate made a mistake, or almost made a mistake, I added to my list of things to look for.

You can take this list, alter it, and make your own checklist. Then, use the checklist each time a drawing passes over your table. Not every check I list below will apply to every drawing, obviously.

P&ID Checklist:

Does this drawing include, where appropriate:

  • My company’s document/drawing #
  • Client document #
  • Licensor/Vendor document #
  • Title block: including the By/Approved/Checked blocks filled and signed, Date, Rev. all company logos, client signoff block?
  • All equipment tagged, title above equip, spelling of names correct?
  • Not crowded: Normally have about 4 pieces of equipment per drawing
  • Where feasible, streams come in the left side and go out the right side fo the drawing.  Battery limits are marked. Stream tags include the fluid, drawing #, note the equipment name and tag the stream is from/going to
  • Line arrows are on each turn of a line, in the correct direction?
  • Vessels – Size, design temperature/design pressure, full vacuum, internals/levels, skirt height to grade
  • Heat exchangers – Area, design temp/pressure, duty, motor horsepower (air coolers), conderser/reboilers have elevation, motors have controls
  • Heater – size, duty, design T/P, coil arrangement, utilities on a separate page
  • Boiler – size, design T/P, superheater outlet T, utilities own page
  • Tank – size, capacity, type, heaters/agitators shown
  • Pump rated flow, horsepower, differential head. Showing temporary strainers, drains, motor w/ controls
  • Turbines – in/out temp/pressure, horsepower, strainers
  • Compressor – Actual Cubic Feet per Minute inlet, discharge pressure, driver type, horsepower, strainer, lube/seal oil
  • Instruments are right type, local/transmitted, control type, block/bypass valves shown
  • Instrumentation signal lines are correct line type, local/DCS code correct
  • Control valve type, failure mode shown, block/bypass valves, reducers, the sizes used are the latest from controls department
  • Pressure Relief Valves: set pressure, PSV size is latest, inlet/discharge size and pipespec match latest calculations, outlet lines are Car Sealed Open or have no valves (if to atmosphere), the relief outlet goes to drain/flare/atmosphere
  • Lines connecting to a main flare line connect to that line from above, even making a detour if necessary. (This is an old drafter’s trick to remind pipers that flare lines need to slope downward to drain properly)
  • Block valves: show if they are normally open or closed, car sealed open or closed?
  • Drain valves present, use smaller gate valve symbol, they are between checks/gates/etc
  • Minor valves are placed logically (check valve near pump discharge, swing blind near a gate valve)
  • Spectacle blinds are correctly shown normally open/closed and they are on the side of the valve facing the “danger” (i.e. pressure source, contamination source)
  • Steamouts/steam connections where required? Full vacuum rating on equipment when required
  • Pipe specs are all shown and correct, spec breaks over valves/PSVs, steam and electrical tracing is shown
  • Double-block valves (with 3/4″ drain between) where procedures say there are needed (normally 600 psig+ or dangerous fluids like acid)
  • Insulation is shown on equipment and pipes?
  • Tie Points are at all old/new line interfaces
  • Lines connect to each other according to project’s branch table (e.g. do I need to show an expander before tee?)
  • Show slopes, elevations,
  • Note whenever any items must be within sight of each other (e.g. ensure level gauge can be seen by someone operating this manual globe valve)
  • Utility P&IDs tie in correctly to main drawings, and show connect to utility stations & analyzers
  • Neat DWG, no dog-legs/bad-connections
  • When lines cross, vertical lines break for horizontal lines except that instrumentation lines break for process lines. (This rule varies by company)
  • Matches Process Flow Diagram (PFD) connectivity,
  • Equipment names match other documents like the PFD, equipment list, datasheet, etc.
  • All Notes/Holds are ok? Is it clear what they refer to? Spelling? Are the general project notes and holds, that must be added to each drawing, in place?
  • All the mark-ups were applied by the drafters correctly, spelling is correct
  • Check the drafting process did not introduce any random new errors or mistakes. (Sometimes during a revision, a drafter’s template will be set wrong, or a line type will change for no apparent reason, causing a little mistake. And no one will be looking for it, because everyone just focuses on the areas that were marked up!)
  • Do your own mini-HAZOP of the process: can any deviation in normal temperature, pressure, flowrare, operator mistakes, utility failures, etc. cause a safety problem? Are any remaining safety issues going to be properly documented for the operators
  • Similarly, can you think of any operability problems? Any common maintenance tasks that cannot be done here? Or any practical problems building or installing what you’ve planned?
  • Taking a look at the set of P&IDs as a whole, the stream connections between the drawings are correct (all inlet streams match to outlet streams somewhere, or at least has an adequate explanation)
  • I cannot get rid of any HOLD notes on these drawings
  • I feel satisfied that I’ve done enough work to sign this document. I have no ethical qualms or bad gut feelings

As you work more with P&IDs, you will naturally begin to pick up on mistakes as your instincts build up their own checklist.

You can share any omissions from my list with other readers by leaving a comment.

BONUS: Another piece of old lore I read on eng-tips.com long ago:

When you finish a drawing, correct it, and make it perfect. Then put it in your desk and go home and sleep.

In the morning, pull it out, and correct all the mistakes that you missed.

This is very true. If you can sleep on a drawing, you’ll catch more mistakes. Not that modern project deadlines ever let you apply this rule…

Lastly, keep in mind that no matter how hard you try and how experienced you are, there is still a rate of human error. This is a natural part of human nature and it can happen no matter how careful you are. So keep up with having experienced checkers and multiple drawing revisions and design reviews.

Edits:

2009-11-23: Added spectacle blind

Popularity: 100% [?]

  • Share/Bookmark

Related posts:

  1. Tie Point Procedure on P&IDs
  2. Introduction to Pressure Relief Valve Design Part 3 – Sizing Orifices and Piping
  3. Fluid Controls Institute Articles on Piping Elements
  4. Microsoft Visio Guidelines, Tricks, Keyboard Shortcuts
  5. Assign Control Valve Pressure Drops

3 Responses leave one →
  1. Steve Hunt permalink
    November 5, 2009

    More of a question.

    Normally open/closed valves on P&IDs. Are they shown that way from bench conditions or normal operating conditions? I’m in a heated arguement. I say it’s normal operating conditions.

    • admin permalink*
      November 9, 2009

      Steve, I’ve never heard the term bench conditions before. Can you explain the term more?

      I personally use normally closed valves as an indication to the reader of how the process normally runs. It can be confusing to see a spiderweb of piping and valves and not know how the flow normally goes.

    • Yussouf permalink
      May 6, 2010

      I think the valves or any other control devices must be shown in fail safe condition. That is the condition of the device when they are not activated.
      Thus if a manual valve is left open in normal operating condition it should be shown open. If it left closed (for example, a drain valve) it should be shown in closed condition
      If a Normaly Open (NO) actuated valve is used, it should be shown in open condition

Leave a Reply

Note: You can use basic XHTML in your comments. Your email address will never be published.

Subscribe to this comment feed via RSS

Spam protection by WP Captcha-Free